Steel Mains
Steel Pipe Work / MSCL
Windsor Road (Stage 1)
900mm MSCL
Length 800m
Value $600,000
Client: NACE Civil/RTA/Sydney Water
Windsor Road (Stage 2)
450-900mm MSCL
Length 1.2km
Value $720,000
Client: NACE Civil/RTA/Sydney Water
We also completed stages 4, 5 and 7 obviously a testimony of the quality of our work
Dampier Supply Main Relocation
See description on list
Client Water Corporation
Great Western Highway Project
308-900mm MSCL
Length various portions
Value $3,105,000
Cardiff Market Place
508mm MSCL
Value $1,800,000
Client Woolworths/Hunter Water
Various other projects including valve renewal on 1200mm mains for Sydney Water and several other jobs. Value 6.5million
MSCL water mains (mild steel cement lined Sintakote)
We completed numerous works in MSCL pipe in all sizes from 308mm to 1200mm. Some of these works were of a very critical nature where time was of the essence in highly populated areas at times with only 12 hours capacity in the reservoir, get this type of job wrong and all hell breaks loose as there is no plan B. We have also changed numerous faulty valves from these mains, valves which have been leaking or have failed completely.
The approach that has to be taken with a large steel trunk main that needs work to be done on it is to carefully plan the works. You can only put the most dedicated and qualified personnel on projects such as these and you have to involve the complete team from the start. You also have to work very closely with the asset holder.
We usually start with receiving what the client requires us to do and commence as soon as possible after a full review of the design, with a detailed take off of materials as there is usually a long lead time for pipe of this type and sometimes valves have to be manufactured overseas. You then prepare your site specific plans for approval. Then the major planning commences as you have to arrange welders, heavy lifting equipment and quite a lot of other equipment that you may not use on other types of projects. Also you must have good back up plans for equipment making sure they are freshly serviced and in good working order. Cutting equipment and pumps you have to have duplicates in case of breakdown.
During this period traffic management plans and permits must be put in place as most of the times these types of mains are in very busy urban areas All authorities have to be notified of impending closures especially Police, local hospitals, Council, Residents, Fire dept. so they can plan around the works. There can be a long lead time on approvals for major road shutdowns.
Where the works call for bores we would probably complete these with an outside casing as part of the early works as in most cases these can be completed without causing much disruption to residents or traffic as they are often completed from the road reserves or easements. You would only commence these works once you had proved the entry and exits of the bore for several meters to make sure that the new pipe can be pushed through the bore with spacers so as to centre the new pipe. Afterwards this would be grout filled so as it would probably be maintenance free conduit once it is in place.
When all of the materials have arrived and a full stock take taken to make sure all materials are in place for the works we would plan our crews. Sometimes we may have to work double shifts at critical stages of the works such as valve change out. For the safety of our staff there would have to be a double isolation on the main otherwise a valve could fail while our people are working on it. Safety is a non-negotiable issue where Firedam Civil P/L is concerned. This would mainly happen where connections to the mains are required or on the changing out of valves.
Before we commence the main works and after completing the “Dial Before You Dig”, a full meeting is organised with all the stake holders. This would include management from the authority who is the client together with the superintendent and maintenance staff as well as our team. All issues would be discussed. After this is completed we would commence our works. We would establish our compound together with equipment and materials. If there were long runs of pipe work we would string them out and commence welding straight lengths. After locating existing services with a non destructive vacuum system taking care not to damage them, we would commence laying pipe on a suitable bed in the trench, excavating bell holes for the welders to operate in. As much work as possible would be done above ground for ease and excavators would be used to lift in the pipes. Smaller pipes would be fillet welded with a continuous weld. Larger pipes would have a weld band/ring (sometimes grout filled).
All welds would be reinstated with Denzo wrap and shrink sleeve after welding so as not to allow corrosion to set in. Larger pipes would be repaired on the inside with grout for a smooth finish as per manufacturers’ requirements. Most bends would be pre-made at the foundry but there would also be a provision to manufacturer onsite. Progress for a steel pipe in urban areas should be at the rate of 24 – 36 metres per day, depending on the amount of bends and whether you are in the roadway or in a grassed easement. The pipe would be back filled with sand, warning tape (detectable) is placed 300m above the pipe and either grass put back or road base and hot mix completed at 50m intervals with pits finished level with the surface. All excess material to be tested and disposed of at a licensed facility.
While the main body of works are proceeding all the pipe work and existing pipe work in ground would be recorded for the “As-Constructed” drawings. Compaction tests would be completed as per standards. Planning for connections would be taking place as these always require a large shut down and sometimes have to take place in the winter months when requirements are at lower levels. When the main is laid it is tested and chlorinated to the requirements of the contract. All documentation is presented to the client and the connections can commence. This may require several crews and generally when you start you cannot stop until the main is connected. After all connections are completed, the works are restored. All remaining documentation is handed over to a very happy client.